All methods

MOORA

Available

Multi-Objective Optimization on the basis of Ratio Analysis. Brauers and Zavadskas (2006)

The idea

Benefit ratios pulling right, cost ratios pulling left
Project A0.3261Project B0.3026Project C0.2998

Right of the zero line: weighted benefit ratios adding to S+; left: weighted cost ratios adding to S-; y = S+ - S-.

  • Zero
  • NPV
  • IRR (%)
  • Payback period (yr)
  • Government income
  • Employment
  • Value added
  • Risk
  • Balance of payments
  • Other criteria
Show as table
AlternativeNPVIRR (%)Payback period (yr)Government incomeEmploymentValue addedRiskBalance of paymentsInvestmentS+S-Net score y
Project A0.04040.0571-0.08030.08470.04270.0851-0.05060.05950.08760.45710.13100.3261
Project B0.06470.0653-0.06250.06350.05690.0574-0.06330.06800.05250.42840.12580.3026
Project C0.08080.0694-0.04460.03390.08540.0425-0.07600.06460.04380.42040.12060.2998

Data: Transition projects (Brauers and Zavadskas 2010).

MOORA divides each value by its column length, adds the weighted benefit ratios and subtracts the weighted cost ratios.

When to use it

  • Many objectives, quick screening.
  • TOPSIS normalization with an additive score.

Algorithm

  1. 1Vector normalization
  2. 2Weighted normalized ratio
  3. 3Benefit and cost sums
  4. 4Net assessment score

    Rank by decreasing y; the unweighted origin sets w = 1.

Used together with

Why these pairs
  • The origin splits an important objective into sub-objectives instead of using weights (Brauers & Zavadskas 2006, 2010).
  • Entropy and CRITIC weights with MOORA for air-conditioner selection in Vujičić et al. (2017).
  • SD then MULTIMOORA for EDM process parameters, as reviewed in Keshavarz-Ghorabaee et al. (2021).
  • Used as a comparison method in the MABAC (2015) and CoCoSo (2019) papers.

Reference example

Brauers, W.K.M.; Zavadskas, E.K. (2010)Matches the printed digits
Details

Brauers, W.K.M.; Zavadskas, E.K. (2010). Project management by MULTIMOORA as an instrument for transition economies. Technological and Economic Development of Economy 16(1), 5-24. doi:10.3846/tede.2010.01

Published example (Appendix C, Table 2; brauers-zavadskas-2010-projects) reproduced by the tests: three projects and nine objectives match to 0.00015 (the paper prints B and C to 3 decimals). The tests also reproduce both 2006 origin examples (Tables 1 and 5) and Vujičić et al. (2017, Tables 7a-7b) with Entropy and CRITIC weights.

Checked by this site's test suite.

Sources

Show 6 sources
  1. Brauers and Zavadskas (2006). The MOORA method and its application to privatization in a transition economy. Control and Cybernetics 35(2), 445-469. https://bibliotekanauki.pl/articles/969961.pdfNo DOI. The ratio system first appeared in Brauers (2004, book); the reference example is from the method authors' open-access paper Brauers & Zavadskas (2010).
  2. Brauers & Zavadskas (2010), Technological and Economic Development of Economy 16(1), 5-24 doi:10.3846/tede.2010.01
  3. Brauers & Zavadskas (2009), Technological and Economic Development of Economy 15(2), 352-375 doi:10.3846/1392-8619.2009.15.352-375
  4. Vujičić, Papić & Blagojević (2017), Tehnika 72(3), 422-429 doi:10.5937/tehnika1703422V
  5. Hafezalkotob et al. (2019), Information Fusion 51, 145-177 doi:10.1016/j.inffus.2018.12.002
  6. pyDecision 5.1.1, moora_method and multimoora_method github.com/Valdecy/pyDecision